1、车集站内道口翻修施工组织设计永煤公司铁路运输处8目录1工程概况···················································································32工程施工组织·········································································32.1组织机构······················································

2、························32.2劳力组织···············································································32.3施工前准备工作···································································32.4时间安排····························································

3、···················42.5施工方法···············································································43施工防护8措施……···································································44施工所需机具、材料······························································

4、·54.1施工所需机械、工器具························································54.2施工所需材料······································································65工程概算···················································································6车集站内道口翻修施工组织设计1工

5、程概况车集站站内道口是车集洗煤厂排矸石用道口,现为木枕式混凝土道口板铺面,由于过往排矸车辆较多8,载重量大,造成道口铺面板损坏、道口线路病害严重,危极行车安全,为了恢复道口良好状态,保证铁路行车安全,现对车集站4、5道站内道口进行翻修,同时更换失效木枕,此工程由工务段负责组织施工。2工程施工组织2.1组织机构郑伟负责施工全面管理与协调工作,为施工总负责人;徐强负责现场技术指导;车集工区工长王明行(手机号为13569367345)负责现场劳力组织及施工作业;副工长李永平负责安全防护。2.2劳力组织:施工人员由车

6、集、城郊工区人员组成。2.3施工前准备工作序号工作内容任务完成截止时间责任单位任务要求1与车集洗煤厂联系封锁施工事宜施工前3天运输科1联系汽车施工前2天供应科2用汽车拉道碴20方施工前1天工务段放在道口两侧空地上3用汽车拉木枕施工前1天工务段放在道口两侧2.4时间安排2.4.1计划工期:1天。82.4.2施工当日所有施工人员上午7:00准时到现场,做好施工准备。上午7:30至8:30同时拆除4、5道道口的铺面,挖轨枕空及轨枕头外部碴土,计划8:30要点封锁线路开始施工,处调度给点封锁后,抽出轨枕、挖碴土,到1

7、0:00完成;10:00后,开始上碴铺枕捣固,进行线路整修,11:30恢复线路,11:30至12:30开始机车压道并检查整修后,12:30到13:30铺道口板,13:30解除封锁,恢复道口通行。2.5施工方法2.5.1采用2.50米木枕(一类木枕几何尺寸为长×宽×厚=2500毫米×220毫米×160毫米)更换道口线路木枕。2.5.2为了预防道口翻浆,道口道床道碴厚度设计为300毫米。2.5.3道口线路恢复好后,轨枕捣固打八面镐,列车辗轧4遍后线路达到稳定,再铺道口板。3施工安全防护措施为确保车集矸石道口施工安

8、全,特制定如下安全防护措施:3.1在站内登记要点封锁后方可施工。3.2施工前召开全体施工人员安全现场会,进行安全措施贯彻和教育,安排具体施工内容,明确责任分工,传达安全注意事项。83.3施工现场,车集工区工长王明行为现场负责人(手机号为13569367345),并负责与车站联系施工相关事宜;同时负责组织现场作业人员按章作业。3.4在抬木枕作业时,要达到用劲均匀,动作一致,确保安全。3.5施工过程中,

当前文档最多预览五页,下载文档查看全文

此文档下载收益归作者所有

当前文档最多预览五页,下载文档查看全文
温馨提示:
1. 部分包含数学公式或PPT动画的文件,查看预览时可能会显示错乱或异常,文件下载后无此问题,请放心下载。
2. 本文档由用户上传,版权归属用户,天天文库负责整理代发布。如果您对本文档版权有争议请及时联系客服。
3. 下载前请仔细阅读文档内容,确认文档内容符合您的需求后进行下载,若出现内容与标题不符可向本站投诉处理。
4. 下载文档时可能由于网络波动等原因无法下载或下载错误,付费完成后未能成功下载的用户请联系客服处理。